Claire Brereton said:
I am trying to do something very simple - report how much of my project is
actually complete and how much I had planned to be complete.
None of the Help can show me how to do this. I know you have to baseline the
project but all of the fields seem to refer to $$ not hours.
Claire,
I assume you are looking at the earned values metrics (i.e. ACWP, BCWP,
& BCWS). These are in fact all based on the classical premise that,
"time is money". I don't agree with that philosophy 100% but it is the
classical approach.
Although it is not quite what I think you want, there is a field called
Work Variance that might give you some useful information. You can read
more about it in the help file.
If you really want a metric describing planned (i.e. baseline) work at a
point in time (e.g. status date) compared to actual work at that same
point in time, you will probably need to use VBA. A formula in a custom
field will not work because you need the timescaled data for comparison
and timescaled data is only available through VBA.
If VBA is not an option for you, with a little work the data can still
be obtained. If Cumulative Work and Baseline Work are displayed in one
of the Usage views (i.e. Task or Resource), you can manually add up the
Baseline Work hours and compare it to the Cumulative Work hours as of
the date of interest. You can then manually enter this information into
a spare field on the view so it can be saved or printed. Not real
convenient but it will get you there.
Hope this helps.
John
Project MVP