Is there a database function where I can save tasks and their corresponding
sub-tasks for future projects? Many of my projects use the same tasks and
sub-tasks. Instead of having to enter everything again for each new project,
can I go to a stored memory function and select the tasks that I need so that
they are automatically entered under the Task Name column?
 
G

Gérard Ducouret

Hello,
Use the "Model" feature :
File / Save As... / Type : Model (.mpt) instead of Project (.mpp)