T
Twinkletoes1971
I have a task that is 30 days long and needs to finish by a specific date.
however the task is only 10 days work.
I need to get Project to let me leave the duration at 10 days and the start
and finish dates 30 days appart.
I've tried Fixed work and Fixed durations but it always reduces the task
length to 10 days.
Can anyone help?
however the task is only 10 days work.
I need to get Project to let me leave the duration at 10 days and the start
and finish dates 30 days appart.
I've tried Fixed work and Fixed durations but it always reduces the task
length to 10 days.
Can anyone help?