How do I set a milestone at the end of a task duration?

D

db8791

I would like to set as a milestone the end of a task with a duration, but it
seems to want to place the milestone at the beginning of the task. Is there
a way to do this without setting the task duration to "0"?
 
R

Rod Gill

Hi,

Firstly the end of a task is an event in any case so why the milestone?

A milestone is a separate task and is created by setting a duration of 0d

To put it after another task, link the task to the milestone.
 
J

Jan De Messemaeker

Format
Bar Styles
Look for the Milestone line
In teh From and To columns replace Start by Finish
HTH
 