I am creating a schedule for heavy construction. Because work stops during
the winter months, I want to set Jan, Feb, & Mar, as non-working time. I
cannot find a way to do this, other than building in lag time.
This isn't how I want to do it, because if I make changes to the schedule, I
always have to review the impact around those months.
Anyone know how I can set certain months as non-working time?