I need to show a task that occurs on a weekend. Its not actualy a task
being performed by the people on the project so I do not want to
modify the calandar which would cause MSP to schedule the real work
during that time. I just need to represent the task in the project
because it is something we have to be aware of. I need to show it
during non-working time.

How can I do this?
Thanks
 
R

Robert H

I figured it out, just create anouther calandar to assign the task to.
Like you would of you needed to show paint drying.
 