S
sknapp
I am a first time user of Project, I have Project 2003 at work. I thought it
would be a geat tool to track some contract options I want to bereminded of.
The concept is I have several department s where I work that have contracts
that have options to extend the contract before it expires. I want to set
something up that lists all the contracts per department with the contract
original dates, an erercise option date and how long the option will extend
the contract date. Also I want a filed that will remind me 180 days, 90 days
and 60 days before the exercies option date so I don't miss the important
exercise option date.
I don't need anything to do with units of people or duration of hrs worked,
just a simple calendar that shows me important dates (milestones).
Is this possible?
Thanks for your help!
Sandy
would be a geat tool to track some contract options I want to bereminded of.
The concept is I have several department s where I work that have contracts
that have options to extend the contract before it expires. I want to set
something up that lists all the contracts per department with the contract
original dates, an erercise option date and how long the option will extend
the contract date. Also I want a filed that will remind me 180 days, 90 days
and 60 days before the exercies option date so I don't miss the important
exercise option date.
I don't need anything to do with units of people or duration of hrs worked,
just a simple calendar that shows me important dates (milestones).
Is this possible?
Thanks for your help!
Sandy