How do I show 1 resource for 2 days at the start & end of a task

T

Tom Anderson

I require 1 Resource for 2 days at the start and end of an 11 day task which
has 2 other resources working on it full time.
 
J

Jan De Messemaeker

Hi,

In the task usage view you can contour the work for each resource as
necessary.
HTH
 