V
VK
How do I show only the activities for the next 2 month from a larger program
and hide the others one ?
Thanks
and hide the others one ?
Thanks
Jim Aksel said:I tested your scenario prior to making my post. Using the filter on [Start]
and [Finish] excludes tasks you want to include. Instead, the Date Range
filter will do this for you.
On the Format toolbar is a drop down that says "All Tasks". Hit the drop
down and select "Date Range..." It will ask you:
Show Tasks That Start or Finish after: (enter a date -- 8/23/2007)
And Before: (enter a date -- 9/6/2007)
If any portion of any task lays within these dates it will show.
Specifically:
Starts 1/1/1974 ends 12/31/2030 passes through the window and shows
Starts 1/3/1973 end 8/20/2007 excluded as left of window
Starts 8/28/2007 ends 12/31/2007 shows -- it starts in the window
Starts 1/1/2007 ends 8/31/2007 shows -- it ends in the window
Starts 8/25/2007 ends 8/31/2007 shows -- it is entirely in the window
Starts 10/1/2007 ends 12/15/2007 --- excluded as future task
Try for yourself on a Project1.mpp and watch the behavior.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
VK said:The filters (on 'Start' or 'Finish' dates) allow me to to filter the
activities starting after one date or finishing before/after one date. But it
won't show the tasks in progress but started before or finishing after.
For example: I want to show only the activities in progress during
September. So I want to hide the activities finished before September or not
started in September. But I want to show one activite started in June (for
example) and finishing in September or after.
I hope you will understand my question. Tnaks in advance.
Jim Aksel said:I tested your scenario prior to making my post. Using the filter on [Start]
and [Finish] excludes tasks you want to include. Instead, the Date Range
filter will do this for you.
On the Format toolbar is a drop down that says "All Tasks". Hit the drop
down and select "Date Range..." It will ask you:
Show Tasks That Start or Finish after: (enter a date -- 8/23/2007)
And Before: (enter a date -- 9/6/2007)
If any portion of any task lays within these dates it will show.
Specifically:
Starts 1/1/1974 ends 12/31/2030 passes through the window and shows
Starts 1/3/1973 end 8/20/2007 excluded as left of window
Starts 8/28/2007 ends 12/31/2007 shows -- it starts in the window
Starts 1/1/2007 ends 8/31/2007 shows -- it ends in the window
Starts 8/25/2007 ends 8/31/2007 shows -- it is entirely in the window
Starts 10/1/2007 ends 12/15/2007 --- excluded as future task
Try for yourself on a Project1.mpp and watch the behavior.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
VK said:The filters (on 'Start' or 'Finish' dates) allow me to to filter the
activities starting after one date or finishing before/after one date. But it
won't show the tasks in progress but started before or finishing after.
For example: I want to show only the activities in progress during
September. So I want to hide the activities finished before September or not
started in September. But I want to show one activite started in June (for
example) and finishing in September or after.
I hope you will understand my question. Tnaks in advance.
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.