How do I show "Planned Hours to Date" in project?

R

R Heaberlin

I looking for a way to show the planned hours to date for each task in my
project plan.
 
J

Jan De Messemaeker

Hi,

In task usage view, insert the line Cumulative work
(Right Click, Detail styles,select Cum Work, Show)
Read today's value.
HTH
 