P
Project_Info_Seeker
AM trying to create an Assignment sheet for the resources on my project. It
can't have the work column on it (I don't want the resources to know how many
hours there are allocated. They burn them all if they know they're there).
I've tried working with "who does what when", but can't seem to get the work
column removed from the details. I've been able to get them out to the "To
Do List" report by removing the work column from a copy of the entry table
and using that copy as the reporting table. However, I can't seem to figure
out how to make the Resource's name appear on the report.
Thanks
can't have the work column on it (I don't want the resources to know how many
hours there are allocated. They burn them all if they know they're there).
I've tried working with "who does what when", but can't seem to get the work
column removed from the details. I've been able to get them out to the "To
Do List" report by removing the work column from a copy of the entry table
and using that copy as the reporting table. However, I can't seem to figure
out how to make the Resource's name appear on the report.
Thanks