M
mike
Heya guys,
I have a resource with a standard working time (8-12, 1-5). He stayed
late on a Friday because the project was behind, started and finished
the task and finished the task (4 pm to 8:30 pm, outside the normal
time). When I try to enter the actual task finish time outside the
resources working time, project turns the task into a milestone. When
I try to enter the actual duration instead, it shows the task
completing Monday morning.
Is there a way to get the actual time to show on project when its
outside the resource's calendar?
Thanks,
Mike
I have a resource with a standard working time (8-12, 1-5). He stayed
late on a Friday because the project was behind, started and finished
the task and finished the task (4 pm to 8:30 pm, outside the normal
time). When I try to enter the actual task finish time outside the
resources working time, project turns the task into a milestone. When
I try to enter the actual duration instead, it shows the task
completing Monday morning.
Is there a way to get the actual time to show on project when its
outside the resource's calendar?
Thanks,
Mike