How do you make the entire week workdays?

L

Lucy2000

Just wondering how you woould make it so that the entire week (all 7 days)
are listed as workdays?
Thanks
 
J

JackD

Tools menu / change working time / edit calendar, or simply use the 24 hour
calendar.
 
M

Mike Glen

Hi Lucy,

Welcome to this Microsoft Project newsgroup :)

Tools/Change Working Time..., click and drag across the S and S for the
weekend so that they are all highlighted, make nondefault working time/OK.
Whilst we're on the topic, you might like to see FAQ Item: 5. Default
Working Hours.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 
P

Perfect Reign

Just wondering how you woould make it so that the entire week (all 7 days)
are listed as workdays?
Thanks

Easy - tools - change working time

There'll be a cool little pop up box where you can setup times to your
heart's content

HTH
 
S

Steve House [MVP]

There are several reply already telling you how to do this, but I should
add - Are you sure you really want to? Since the calendar controls the
scheduling of tasks and tasks usually are proken down to the level of the
work done by one person or a team of individuals, showing all 7 days as
workingg days implies that once a task starts, people will work on it every
day, no days off at all, until it' done. Before setting up your calendar as
7 days you should make sure that really describes what's going to happen
with your tasks. If there's a task that takes 2 weeks to do, will it be
worked on every day for 2 weeks without the people working on it taking any
days off?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top