how do you show original vs. fcst/actual milestone dates using a g

T

tim

I want to show tasks with their original milestone dates and any slippage on
the same line linked by a line. Ideally colour coding them with a RAG.
 
J

Jan De Messemaeker

Hi,

To keep the original milestone dates: Tools, tracking, Save Baseline
To create your very own bars read FAQ 31
Faqs URL is in my signature
Hope this helps
 
T

tim

thanks for your comment.
However, this seems to cover how you highlight and colour a particular
resource.

I have saved the baseline milestone.

I want to show this one and also a revised milestone date on the same line
in the gantt chart.

regards
Tim
 
J

Jan De Messemaeker

Hi,

You're right, it is less general than what I had in mind.
I'll explain how but mind you the Tracking Gantt view has exactly what you
are looking for so if my explanations wouldn't be enough, you can always
have a look on the Bar styles of the Tracking Gantt View
You have the milestone losenge haven't you? It represents current plan
To add a symbol representing the milestone baseline date:

In Bar Styles add a line
Name : Baseline Milestone (or whatever)
Appearance: select a start shape and a color
Show For... Milestone
Row 1
From Baseline Start
To BaselineStart

Hope this helps
 