How do you split the work in hours, among the resource instead of percentage ?

K

ks2008

When you assign, multiple resource to a particular task, you go to
Assign Resource (Alt + F10) window and split the work among the resource
in percentage.

For example, if you have a work of 80 Hours, you can split the work
into 60%+40% ratio among the two resource. How do you split the work in
hours, among the resource instead of percentage ?

Thanks
KS
 
R

Rod Gill

Hi,

If you turn off Effort Driven for a Task (I always have this off by default
(Tools, Options) then you can enter hours against Resource Names, EG: 40h
(without the h 40 is 40% by default).

Otherwise you will need to use the Task Usage View to manually adjust work
share or Window, Split and manually adjust hours in the Task Form.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




ks2008 said:
When you assign, multiple resource to a particular task, you go to
Assign Resource (Alt + F10) window and split the work among the resource
in percentage.

For example, if you have a work of 80 Hours, you can split the work
into 60%+40% ratio among the two resource. How do you split the work in
hours, among the resource instead of percentage ?

Thanks
KS


--
ks2008
------------------------------------------------------------------------
ks2008's Profile: http://forums.techarena.in/members/106957.htm
View this thread: http://forums.techarena.in/microsoft-project/1251969.htm

http://forums.techarena.in


__________ Information from ESET Smart Security, version of virus
signature database 4462 (20090927) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4462 (20090927) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
S

Steve House

The assignment percentages are NOT the split of the task's work between
them. The percentages are rate indicators indicating the relationship
between the full-time equivalent work abnd the time it takes. If a resource
is assigned 100% to an 8 man-hours task it will take him 8 hours to do it.
But if he's assunged 50%, what he COULD have done in 8 hours time will
in-fact take him 16 hours.
 
K

ks2008

I have modified my resource sheet inserting several new column.
Now I wanted to go back to default resource sheet
Could I do that ? How Do I do the same
thank
K
 
M

Mike Glen

Hi ks2008,

Welcome to this Microsoft Project newsgroup :)

Right click the unwanted column and select Hide. If you want to keep your
current view, View/More views... select the Resource Sheet on the left of
the dialog and Copy... Give it a useful name and OK. Now hide the columns
you inserted until they're back to the default.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 