how does Project calculate summary progress

T

Tomcat

Also if anyone has any further comments on the "Work schedule progress
question" post below it would be greatly appreciated
 
J

John

Tomcat said:
Also if anyone has any further comments on the "Work schedule progress
question" post below it would be greatly appreciated

Tomcat,
This question has been answered multiple times in the past. The short of
it is as follows:

Summary Line percent complete = (sum of subtask Actual Durations) / (sum
of subtask Durations) x 100%.

Note that subtasks are actual performance tasks. Using duration values
of other Summary lines does not work in the equation.

Hope this helps.
John
 