New2Project said:
Just wondering, how does Project work out whether a task is critical? Is it
when you set a task to 'Finish no later than'?
How do you then also make a task critical?
Thanks
New2Project,
Yes, Project calculates critical path based on one of two things. Either
it encounters a constrained task (e.g. finish-no-later-than) or the last
task in the plan (which often is constrained to meet some end goal
milestone).
Critical path is based on the setting for Total Slack (see
Tools/Options/Calculation tab - bottom of the Options window). Normally
the idea is to get tasks OFF the critical path (otherwise the plan isn't
going to finish on time). Tasks become critical when they slip or
otherwise are moved to cause their Total Slack to be equal to or less
than the critical path setting.
Hope this helps.
John
Project MVP