how i change in calendar view starting day as saturday?

L

Lina

I want to change the MS Project calendar view means i want saturday should
display first rather than monday because my starting day is saturday.
Thank you.
 
G

Gérard Ducouret

Hello Lina,
Tools / options / calendar / Week starts on : sunday

Gérard Ducouret
 
L

Lina

Thanks for reply but my problem didnot solve.
Tools / options / calendar / Week starts on : sunday ; if i apply this
setting it shows starting day as sunday rather than saturday.
Is there any other way.
Please let me know.

Lina
 
G

Gérard Ducouret

Sorry, my keyboard is faster than my reading ;-(
Tools / Options / Calendar / Week starts on : Saturday !!!

Gérard Ducouret
 
L

Lina

Hi
I tried this option. But its showing monday as start day rather than
saturday on my MS Project calendar view.
Is there any other way to do that please let me know.
Thank you.
 
G

Gérard Ducouret

Lina,
I tested in Project Pro 2003 and it works fine...
What is the version you are working with ?

Gérard Ducouret
 
L

Lina

Hi

Thanks for your effort. I am also using MS Project Pro 2003. But its only
changing the view of Gantt Chart but not on the Calendar view. In the
Calendar view its showing Monday as starting day.
Sorry i am disturbing you lot.
Waiting for your reply.
Have a nice day.
 