L
LRamirez
The schedule is already created with the start and finish date by task. Then
I realize that I forgot set two holiday as non working days, Is posible two
set as nonworking dates but without changes the start and finish dates f0.or
all tasks?
I realize that I forgot set two holiday as non working days, Is posible two
set as nonworking dates but without changes the start and finish dates f0.or
all tasks?