How set start and finish date, then change the working dates

L

LRamirez

The schedule is already created with the start and finish date by task. Then
I realize that I forgot set two holiday as non working days, Is posible two
set as nonworking dates but without changes the start and finish dates f0.or
all tasks?
 
M

Mike Glen

Hi LRamirez ,

Welcome to this Microsoft Project newsgroup :)

No, at least not automatically. If people won't be working during the
non-working days, the Duration will increase accordingly. You can recover
that by making them work the equivalent amount of overtime.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 