How to add a gridline in gannt chart to show Deadline?

M

microbus73

Need to add a gridline through Gantt chart deadline to show Deadline so that
it shows items that go beyond the deadline for the entire project. Is that
possible
 
J

Jan De Messemaeker

Hi,

Insofar you do not use the status date for other calculations, you can make
it show your deadline (Project, Project Information) and show the gridline
for status date.
HTH
 
S

Steve House [MVP]

Use the drawing tools to put a vertical line in the plan and in the line
properties lock it to the date. A better way than a vertical line would be
to insure you have a final "Project Complete" milestone and all dependency
link paths terminate on it - while not every task in a project will have a
predecessor necessarily, every one will have a successor - if nothing else,
the Project Finished milestone. Then set a deadline (Task Information,
Advanced tab) on the finish milestone. Now MSP will "red flag" if you're
going past the deadline. You could carry it farther and put a deadline on
all the tasks in the plan if you like but I don't think that would be
particularly valuable.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top