Hi Matteo,
Okay, thanks for the additional information. I don't use Project server
so I can only tell you how it works using Project desktop, but I believe
the issue is the same. As you are using Project Server (and I assume
enterprise resources), if you have follow up questions, you may want to
post those to the Project Server newsgroup. This newsgroup is focused
on the desktop usage (non-server.)
If you want to use resource costs for the analyst and systems
administrator based upon Standard, Overtime and/or Cost per use that you
define in the Resource Sheet, the resources cannot be defined as budget
resources. They need to be created as work resources or cost resources,
but de-select the "budget" check box on the resource information tab.
Then you can fill in the cost (Standard Rate , Overtime Rate, Cost per
use) on the Resource Sheet. Costs from the standard rate will carry
through when you assign the resource to tasks based upon the amount of
work for the resource. Overtime cost is based upon overtime work
assigned.
Resources (work and cost) resources that have been set as budget
resources can only be assigned to the Project summary task. You add the
cost for the budget resources on the assignment (look at the Task Usage
view) for the project summary task. In the Task Usage view, add the
cost field to the table and enter the costs there.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project