How to add Enterprise Task Outline and Enterprise Resource Outline to Project Center view?

H

hale

hi everyone:
How to add Enterprise Task Outline and Enterprise Resource Outline to
Project Center view?
I want to view Project by Enterprise Task Outline and Enterprise Resource
Outline.
thank you for any help!
hale
 
D

Dale Howard

Hale --

The Project Center views can only display project level fields, such as the
Enterprise Project Outline Code field. It cannot display Enterprise Task or
Resource Outline Code fields. Sorry.
 