M
Marky
Hi all,
I'm new here but have been a (periodically frustrated) MSP user for some
time now... One thing that we've always tried to do but never managed to
achieve cleanly is schedule a background task (for example maintenance or
support activity for a software project) that can sweep up resource
availability across the project automatically.
For example if we are a team of 4 developing an iteration of a software
product, and we are also expecting 1 FTE worth of effort across the team to
be dedicated to fixing bugs that come through, I'd like to set up a
background task, assign it 4 resources, and have it 'soak up' any spare
availability from the team.
Or to put it another way, automatic resource levelling would allocate
maximum units to formally planned tasks and any spare units to the 'bug
fixing'. The amount of unti allocation would change as I change the formally
planned tasks. Naturally if there were not enough spare units from the formal
plan to support the desired effort required in the bug fixing task, I'd
expect the schedule to expand accordingly.
The reason we need this is that day to day, developers activities change,
and the only way I can see of achieving the above is to block out one
resource to do the bug fixing at 100% allocation. This makes day to day
tracking enourmously fiddly as a day not spent on bug fixing by this resource
has to be manually re-allocated.
I spotted the use of 'Maintenance and Operations Work' here
http://blogs.msdn.com/dieterz/ but this looks like it's in the enterprise web
based interface for server 2007 - not in project itself...
Help ! (appreciated) !
I'm new here but have been a (periodically frustrated) MSP user for some
time now... One thing that we've always tried to do but never managed to
achieve cleanly is schedule a background task (for example maintenance or
support activity for a software project) that can sweep up resource
availability across the project automatically.
For example if we are a team of 4 developing an iteration of a software
product, and we are also expecting 1 FTE worth of effort across the team to
be dedicated to fixing bugs that come through, I'd like to set up a
background task, assign it 4 resources, and have it 'soak up' any spare
availability from the team.
Or to put it another way, automatic resource levelling would allocate
maximum units to formally planned tasks and any spare units to the 'bug
fixing'. The amount of unti allocation would change as I change the formally
planned tasks. Naturally if there were not enough spare units from the formal
plan to support the desired effort required in the bug fixing task, I'd
expect the schedule to expand accordingly.
The reason we need this is that day to day, developers activities change,
and the only way I can see of achieving the above is to block out one
resource to do the bug fixing at 100% allocation. This makes day to day
tracking enourmously fiddly as a day not spent on bug fixing by this resource
has to be manually re-allocated.
I spotted the use of 'Maintenance and Operations Work' here
http://blogs.msdn.com/dieterz/ but this looks like it's in the enterprise web
based interface for server 2007 - not in project itself...
Help ! (appreciated) !