A
Android
We're using project Server 2002
In our implementation, Project Server treats 1 day as 8 hours of work, and
Project Professional treats it as 7.5 hours or work. This means if a team
member creates a 1 day task via PWA, it shows up in the schedule at starting
at 8.30AM on start date and ending at 9AM on the next day.
I have not been able to find how to change the working time on PWA to 7.5
hours. How do I do this??
In our implementation, Project Server treats 1 day as 8 hours of work, and
Project Professional treats it as 7.5 hours or work. This means if a team
member creates a 1 day task via PWA, it shows up in the schedule at starting
at 8.30AM on start date and ending at 9AM on the next day.
I have not been able to find how to change the working time on PWA to 7.5
hours. How do I do this??