I would like to define a task that must happen continously once started. For
example I would like to create a task that may take 6 hours to perform.
However, once it is started it cannot be stopped until finished.
When I tried to create a default task, I had 2 hours remaining in my day.
Then Project scheduled the task to start, work for 2 hours, then on Monday it
finished the remaining 4 hours of work. If it cannot get the job done on
Friday, then I would rather have it wait until Monday to start the job. How
would I do this?
Thanks for your help.
example I would like to create a task that may take 6 hours to perform.
However, once it is started it cannot be stopped until finished.
When I tried to create a default task, I had 2 hours remaining in my day.
Then Project scheduled the task to start, work for 2 hours, then on Monday it
finished the remaining 4 hours of work. If it cannot get the job done on
Friday, then I would rather have it wait until Monday to start the job. How
would I do this?