P
Prihadi R.
Hi,
I have a project situation where a resource will work with this kind of
rule: 30 days work (including weekends) followed by 28 days of Holiday
(including weekends), then this rotation will recurring again.
Another information is that 1 day before the a resource entering his/her 28
days holiday another resouce will take cover the work with the same working
rotation rule (30days work + 28days holiday).
Example : A working from day 1 - day 30 then will have holiday from day 31
till day 59, while B will start working from day 29 then will have holiday
from day 57, and the task will recurring back to A then B ,etc.
Is it possible to create a task that takes 3years and when I assign the
resources (A & B) it can show the working rotation for that resources?
(30days work - 28 days holiday - 30 days works - ...)
Hope I describe the situation clear enough. Any help will be very appreciated.
Pri
I have a project situation where a resource will work with this kind of
rule: 30 days work (including weekends) followed by 28 days of Holiday
(including weekends), then this rotation will recurring again.
Another information is that 1 day before the a resource entering his/her 28
days holiday another resouce will take cover the work with the same working
rotation rule (30days work + 28days holiday).
Example : A working from day 1 - day 30 then will have holiday from day 31
till day 59, while B will start working from day 29 then will have holiday
from day 57, and the task will recurring back to A then B ,etc.
Is it possible to create a task that takes 3years and when I assign the
resources (A & B) it can show the working rotation for that resources?
(30days work - 28 days holiday - 30 days works - ...)
Hope I describe the situation clear enough. Any help will be very appreciated.
Pri