L
LAM
I need to enter a task that is actually a meeting. I anticipate that,
arranging the various schedules for the meeting is going to take from 1-5
days.
I want to assign all the people involved in the meeting as resources, the
problem is that I do not want to appear in MS Project as they worked 8 hours
a day for 5 days, when the meeting is only going to be a 2 hours meeting in
only one day.
How should I enter this task?
Thanks.
arranging the various schedules for the meeting is going to take from 1-5
days.
I want to assign all the people involved in the meeting as resources, the
problem is that I do not want to appear in MS Project as they worked 8 hours
a day for 5 days, when the meeting is only going to be a 2 hours meeting in
only one day.
How should I enter this task?
Thanks.