Sorry, this is not possible in Project. If you planing is typical for that
small a period, you could plan it in minutes and let it be known that 1 min
= 1 sec.
FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/
Hope this helps - please let us know how you get on
Any time I want to schedule and track tasks of very short duration, such as
"verify equipment has been delivered", I set it up as a 'milestone' (0 in
duration column) which can still be scheduled and marked as 'complete' and
have dependencies, etc.