I have a full schedule running a large project and need to be able to show a
two week look ahead to the owners. The size and duration of the project make
the graphic display of the entire project overwhelming for the clien.
 
J

John

Drake said:
I have a full schedule running a large project and need to be able to show a
two week look ahead to the owners. The size and duration of the project make
the graphic display of the entire project overwhelming for the clien.

Drake,
Depending on exactly what you want to see in the "2 week lookahead",
there are various approaches. One simple method is to use the built-in
"Date Range" filter. When applied, it will ask for two dates, one to
define the end of the period and one to define the start.

If for some reason the Date Range filter doesn't give you what you need,
give us more specifics about what you want to see, and we can offer
alternate solutions.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top