How to get the Remaining Availability on a daily basis for calcula

S

Shan

Hi,

When you click on View -> Resource Usage, you get some columns displaying
the resource and data associated to the resource, and you get a calendar on
the right which is available on a daily basis. What i want to do is to get
the Remaining Availability which is available on a daily basis so that i can
use that in a calculation. The idea is that i want to get the Remaining
Availability between any two dates.
 
M

Mike Glen

Hi Shan ,

Welcome to this Microsoft Project newsgroup :)

Right click in the timescale part and select Remaining Availability.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
S

Shan

Hi,

This one I know. But, this data is only visible. I need to be able to get
the value to do some calculations with it in the left pane of the view.
 