How to I calculate the elapsed time in a Project...?

J

JVjB

Hello,

I need what you might consider to be basic help. I want to calculate the
elasped time for the project along the whole timeline of the project. How
can I do this?

All help appreciated.

Regards

Jamie
 
J

Jack Dahlgren MVP

go to the "tools" menu, select "options", on the "view" tab select the "show
Project summary task" option at the lower right.
This will display the project summary task. Its duration is the entire
duration of the project.

-Jack Dahlgren
 
V

vanita

Hi Jamie

Please be little more specific. Do you want to see a bar from Actual project
start date to the Status date, or numerically you want to calculate the
number of days for which the work has happened?

Vanita
 