Hi Christine
There are two ways in which I think you can achieve what you are after.
1. Export relevant data to Excel and then sort on Resource Name and Date,
then insert page breaks at the end of each resource name and print them out.
2. The second way is if you hvae a copy, or can borrow one, of Rod Gills
VBA Programming for Project, there is a Macro in there that exports task
based information to excel based on resource name and date. You can then use
the responses to update project automatically from Excel to Project.
Option 1 might be the easiest for you initially if you are not familiar with
VBA.
If you need some instructions for the Option 1 then let me know.
Kind regards
TonyK