Haixiang said:
the way i know to remove a split is to move the bar in gantt chart, is there
any field that store the split information? Can edit the field to add or
remove split in table?
thanks in advance
Haixiang,
Although there is not a specific field for splits, the effect of a split
task can be readily seen on one of the Usage views (Resource or Task).
The Usage views can also be used to both create and remove splits from
tasks. For example, do a split view with the Gantt on top and one of the
Usage views on the bottom. Set the timescale so the split period of the
task shows in the lower pane (you will see "0h" during the split). To
remove the split, move (or add) hours to the cells in the Usage view
that have "0h". To add a split, move (or delete) hours from the period
where you want to split to occur.
Hope this helps.
John
Project MVP