How to resolve a gap in task ID numbering

C

Carlchat

I have a Project 2003 schedule that's been published to Project Server. In
Project, the task IDs have a gap, like this:
1
2
3
8
9

Tasks 4 through 7 are not shown. The schedule has no filtering, sorting, or
grouping applied. I've tried resorting by ID but with no luck. The missing
tasks 4 through 7 are simply nowhere to be found in Project.

I mentioned that this schedule has been published to Project Server. There,
can see the mystery tasks 4 through 7 in the Project Center view.

Back in Project, I'd like to show the missing tasks 4 through 7, delete
them, and have Project correctly renumber the remaining tasks. Any
suggestions on how to accomplish this?

Thanks, Carlchat
 
C

Carlchat

Bingo! That's exactly right. Tasks 4 through 7 did have external successor
links (I discovered this via the Tools/Links between projects command). I
deleted the external links there , the mystery tasks disappeared, and the
remaining task IDs renumbered correctly. Thanks!
 