I have a Project 2003 schedule that's been published to Project Server. In
Project, the task IDs have a gap, like this:
1
2
3
8
9
Tasks 4 through 7 are not shown. The schedule has no filtering, sorting, or
grouping applied. I've tried resorting by ID but with no luck. The missing
tasks 4 through 7 are simply nowhere to be found in Project.
I mentioned that this schedule has been published to Project Server. There,
can see the mystery tasks 4 through 7 in the Project Center view.
Back in Project, I'd like to show the missing tasks 4 through 7, delete
them, and have Project correctly renumber the remaining tasks. Any
suggestions on how to accomplish this?
Thanks, Carlchat
Project, the task IDs have a gap, like this:
1
2
3
8
9
Tasks 4 through 7 are not shown. The schedule has no filtering, sorting, or
grouping applied. I've tried resorting by ID but with no luck. The missing
tasks 4 through 7 are simply nowhere to be found in Project.
I mentioned that this schedule has been published to Project Server. There,
can see the mystery tasks 4 through 7 in the Project Center view.
Back in Project, I'd like to show the missing tasks 4 through 7, delete
them, and have Project correctly renumber the remaining tasks. Any
suggestions on how to accomplish this?
Thanks, Carlchat