SuzanneD
I am using Project 2003 to analyse room bookings and staff resources required
for a training center.
With about 250 tasks(courses) I would like to set different start and finish
times for these tasks. Some courses are only for a 1/2 day so we may have a
task in the same resource(classroom) for the AM and PM. PJ2003 is displaying
these as a clash.
Any ideas out there besides setting up an individual calendar for every
start/finish option?
"Your bright ideas may be my solution": thanks.