J
Jeff Hu
I have a project which requires 100 days work (Fix work task). I have
several resources available, and I want to set up a max work day they
can be allocated. For example, each resource can only work no more than
40 days.
But, I can't find where to set it. there is a "Max Unit" flag but it
seems it is not what I want.
Can somebody give me a hint.
several resources available, and I want to set up a max work day they
can be allocated. For example, each resource can only work no more than
40 days.
But, I can't find where to set it. there is a "Max Unit" flag but it
seems it is not what I want.
Can somebody give me a hint.