How to sort by flag1 finishing after flag2?

D

damien

Ok, I have two tasks that are identically named. I differentiate them
by Flag1 and Flag2. Flag1 has to finish before Flag2. It does not
matter what level of overlap occurs between the two tasks.

My question is, how can I identify which identically named tasks have
Flag1 finishing after Flag2?
 
J

Jim Aksel

There is probably an easier way than this ... but here's what I would do.
Using one of the custom fields, create a formula. In the formula, you want
to evaluate the dates for Flag1 and Flag2 and place a "True" or "False"
indication as the calculation result. Then, use auto filter and filter this
field to show only "True"

There may be a way to use a custom auto filter directly.
 
J

Jan De Messemaeker

Hi,

Are you aware that Flag fields only have Yes/No as a value so they don't
"finish"?
 