B
bexley
Hi Everyone,
I am working on a Programme which is comprised out of 8 sub projects
some of each comprised of other sub projects.
I am trying to link task from some projects to others. So far so good
but then I have a problem. Let's say that task number 3 of Project A is
linked to task number 4 from Project B on a SS constraint and to task
number 6 from Project C on a SS constraint then I want to add another
predecessor which this time will be from Project A task number 4. This
is where I get stuck. If I want to make task 3 Project A a summary task
as it wont let me outdent the rest due to the links it has with the
other tasks. The thing is I need to have the external predecessors and I
need to have the internal predecessor too so that the time span for task
3 is calculated by all of the others.
How do I do this?
Sorry if I confused you all as I just about confused myself.
Many thanks
I am working on a Programme which is comprised out of 8 sub projects
some of each comprised of other sub projects.
I am trying to link task from some projects to others. So far so good
but then I have a problem. Let's say that task number 3 of Project A is
linked to task number 4 from Project B on a SS constraint and to task
number 6 from Project C on a SS constraint then I want to add another
predecessor which this time will be from Project A task number 4. This
is where I get stuck. If I want to make task 3 Project A a summary task
as it wont let me outdent the rest due to the links it has with the
other tasks. The thing is I need to have the external predecessors and I
need to have the internal predecessor too so that the time span for task
3 is calculated by all of the others.
How do I do this?
Sorry if I confused you all as I just about confused myself.
Many thanks