Can someone please tell me: How can i get auto numbering
such as "1.1, 1.1.1, 1.2, 1.2.1" in the column directly
to the right of the "ID column, and left of the tasks?
What icons do i click, or select, in what order?
 
J

Jan De Messemaeker

Hi,

1. The header of the "Name" column
2. Insert (menu)
3. Column
4. (Select) Outline Number (in Project 98: WBS)
5. OK

HTH

--
Jan De Messemaeker