N
Noel
When I entered my project information, the start and finish dates were not
matching the duration which was in days. So I went into Tools>Options,
Calendar tab and fixed that information to 8 hours a day, 40 hours a week,
and the week starts on Monday. This fixed my start and finish day but once I
changed this information, the duration changed to decimals. For example, 3
days changed to 2.73, 6 days changed to 5.45.
Why does it change the duration to decimals and how can I fix it?
Thanks for your help
matching the duration which was in days. So I went into Tools>Options,
Calendar tab and fixed that information to 8 hours a day, 40 hours a week,
and the week starts on Monday. This fixed my start and finish day but once I
changed this information, the duration changed to decimals. For example, 3
days changed to 2.73, 6 days changed to 5.45.
Why does it change the duration to decimals and how can I fix it?
Thanks for your help