I need to change my schedule to reflect total calendar days total.

A

AL

I need to change the way MS Project reports total project duration.
The default reports reflect total working days, I need to report the
durations in calendar days.

Help
AL
 
G

Gérard Ducouret

AL,
Insert a Date(x) field with a formula like this one:

DateDiff("d";[Start];[Finish];2)*[Minutes Per Day]

Gérrad Ducouret
 
K

ko

Sorry,

But I don't know what a 'Date(x)' field or 'DataDiff' is. I've looked in a
few MS Project books, the MS Knowledge base and I've not found anything that
addresses this topic. Can you explain and/or give me a reference on this
topic?

thanks in advance,



Gérard Ducouret said:
AL,
Insert a Date(x) field with a formula like this one:

DateDiff("d";[Start];[Finish];2)*[Minutes Per Day]

Gérrad Ducouret

AL said:
I need to change the way MS Project reports total project duration.
The default reports reflect total working days, I need to report the
durations in calendar days.

Help
AL
 
K

ko

I don't understand how to use your answer. I've looked in a few MS Project
2003 books, the web, and the MS Knowledge base, but I still cannot find any
references to understand how to implement your advice. Can you point me to a
reference that will explain this to me?

thanks in advance,



Gérard Ducouret said:
AL,
Insert a Date(x) field with a formula like this one:

DateDiff("d";[Start];[Finish];2)*[Minutes Per Day]

Gérrad Ducouret

AL said:
I need to change the way MS Project reports total project duration.
The default reports reflect total working days, I need to report the
durations in calendar days.

Help
AL
 
M

Mike Glen

Hi ko,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #14 & 15, on Customizing Fields, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
I don't understand how to use your answer. I've looked in a few MS
Project 2003 books, the web, and the MS Knowledge base, but I still
cannot find any references to understand how to implement your
advice. Can you point me to a reference that will explain this to me?

thanks in advance,



Gérard Ducouret said:
AL,
Insert a Date(x) field with a formula like this one:

DateDiff("d";[Start];[Finish];2)*[Minutes Per Day]

Gérrad Ducouret

AL said:
I need to change the way MS Project reports total project duration.
The default reports reflect total working days, I need to report the
durations in calendar days.

Help
AL
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top