i want to filter on finish date-all tasks now +2 weeks.please hlp

N

nkgulri

i am looking to filter on the finish date. i would like a view of all tasks
between 3/5-3/19/07. please help!

thank you,
 
J

Jim Aksel

One method is to turn on the auto filters. Project/Filter for... Auto Filter.

Then click the dop down arrow at the top of the Finish Column. Select Custom.
A dialog box will open, set "Greater Than or Equal To:" 3/5/2007 AND "Less
than or Equal To:" 3/19/2007.

If that helps any, please feel free to rate my answer.

Jim
 