P
patrick - md
I am trying to find a way to set a start and finish date based on other tasks.
I have 3 design tasks 18, 35 and 40. I would like to create a single
"milestone" task that looks at these tasks and determines what the first
start date is and what the last finish date is?
For example:
Task 18 has a start date of 4/1/2010 and a Finish date of 4/30/2010
Task 35 has a start date of 4/15/2010 and a Finish date of 5/15/2010
Task 40 has a start date of 4/23/2010 and a Finish date of 5/29/2010.
I would like to create a task called "Milestone - Design" and look at the
start dates of the tasks and select 4/1/2010 as the Start Date since it is
the earliest date of the three tasks and select 5/29/2010 as the Finish date
since is the lastest finish date of the three tasks.
We are using Project Professional and Server 2003.
Any suggestions?
thx.
I have 3 design tasks 18, 35 and 40. I would like to create a single
"milestone" task that looks at these tasks and determines what the first
start date is and what the last finish date is?
For example:
Task 18 has a start date of 4/1/2010 and a Finish date of 4/30/2010
Task 35 has a start date of 4/15/2010 and a Finish date of 5/15/2010
Task 40 has a start date of 4/23/2010 and a Finish date of 5/29/2010.
I would like to create a task called "Milestone - Design" and look at the
start dates of the tasks and select 4/1/2010 as the Start Date since it is
the earliest date of the three tasks and select 5/29/2010 as the Finish date
since is the lastest finish date of the three tasks.
We are using Project Professional and Server 2003.
Any suggestions?
thx.