I want to Filter tasks&fit finish of summary to finish of its sub-

E

Ehsan

Hi, I want to filter the tasks and fit the end of summary to end of its
filtered sub-tasks , it means that i want to fit end of summary based on
filtered task
 
M

Mike Glen

Hi Ehsan,

Welcome to this Microsoft Project newsgroup :)

Summaries are calculated by Project based on the indenting you use. A
filter can only show related summaries and cannot have its own summary.
However, you could create a hammock task to span the filtered task. To do
this it would be best to create a milstone linked to the first task and
another linked to the last task. Create the hammock between them. Then you
would have to include in the hammock whatever parameter you're filtering on.
Please see FAQ Item: 19. Hammock Tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top