P
Pavel Rusyaev
Dear All,
I have just started using MSProject 2000 and cannot find a solution to my
problem. Please be patient.
The question is whether it is possible to set a project to start on Day 1,
Month 1, Year 1 instead of a specific date, such as November 6, 2003. We
need to estimate duration of the project, but project start date is not yet
known.
Thank you,
Pavel
I have just started using MSProject 2000 and cannot find a solution to my
problem. Please be patient.
The question is whether it is possible to set a project to start on Day 1,
Month 1, Year 1 instead of a specific date, such as November 6, 2003. We
need to estimate duration of the project, but project start date is not yet
known.
Thank you,
Pavel