Import data from excel into MS Project

P

projectBewerker

When I import data from an excelsheet (with start end finisch dates-% work
complete ...) by a map into Project. It works , only ...all the tasks are
completed (%work complete = 100%) although this is different from the excel
table !
 
J

Jan De Messemaeker

Hi,

Try to have better luck in English than in Dutch?
I still think you are importing to Actual Finsh date not to finish.
HTH
 
P

projectBewerker

Hi,
that's not the problem becouse I use mapping ( where I can select the item
from a scrollbox so type mismatch is not possible !) . Also , the dates are
correct imported in MS Project ,the only problem is "%Work complete" , this
are not imported from Excel and are default "100%" in MS Project
 
J

Jan De Messemaeker

Hi,

OK.
Can you copy the map into a file (Tools, organizer, Maps) - it is normally
stored in your Global.mpt; and send me that file so that I can have a look.
jandemesATprom-ade.be
 
J

Jan De Messemaeker

Hi all,

Having seen the map: indeed there was an import into Actual Finish.
Case closed.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top