Carol Summa
I have a large project and approximately 25 people sending me weekly
spreadsheets to update their actual hours worked. Not knowing the havoc that
it was going to create, I was importing those spreadsheets into my project
plan and updating the actual work column. Everything was working fine until
I just discovered that the actuals were updating future date. For example,
the plan allocates each resource to work 6.4 hours per day. That's a total
of 32 hours per week. If a resource sends in that they worked on a task for
40 hours that week and I increase the actual work column by 40, behind the
scenes project only puts 32 hours on the current week and then schedules the
rest for the following week.
One, I need to figure out how to get all the hours posted from the past 16
weeks to be backdated so there is no longer future dated actuals. And then,
two, I need to figure out how to post the actual hours by date instead of
just updating the actual work column....or is there a way to tell project to
force any overage to the current billing week.
Any help or insight would be appreciated.
spreadsheets to update their actual hours worked. Not knowing the havoc that
it was going to create, I was importing those spreadsheets into my project
plan and updating the actual work column. Everything was working fine until
I just discovered that the actuals were updating future date. For example,
the plan allocates each resource to work 6.4 hours per day. That's a total
of 32 hours per week. If a resource sends in that they worked on a task for
40 hours that week and I increase the actual work column by 40, behind the
scenes project only puts 32 hours on the current week and then schedules the
rest for the following week.
One, I need to figure out how to get all the hours posted from the past 16
weeks to be backdated so there is no longer future dated actuals. And then,
two, I need to figure out how to post the actual hours by date instead of
just updating the actual work column....or is there a way to tell project to
force any overage to the current billing week.
Any help or insight would be appreciated.