T
Travis
Hi,
I am having trouble importing data into Microsoft Project 2003 from an
Access 97 table. The particular problem is with the import of the start and
finish dates on a task. In some cases the date (usually start date) will not
be updated after the import is complete.
I have confirmed that all the data in the Access table is correct. It
appears to be a problem with Project 2003 import process or some sort of
hidden relationship between start and finsh dates of a task.
Thanks.
I am having trouble importing data into Microsoft Project 2003 from an
Access 97 table. The particular problem is with the import of the start and
finish dates on a task. In some cases the date (usually start date) will not
be updated after the import is complete.
I have confirmed that all the data in the Access table is correct. It
appears to be a problem with Project 2003 import process or some sort of
hidden relationship between start and finsh dates of a task.
Thanks.