Importing into Microsoft Project

M

megan

I use the Project import wizard to import tasks from Excel using the
Microsoft Import Task List Template in Excel.

Everything works fine except when there is more than one resource name
allocated to a task. Is there a specific way of inputting the resource names
in the Excel template so that 2 or more resource names can be allocated to
one task.
 
M

megan

Just to clarifiy - the Excel template I actually use is the Microsoft Project
Plan Import Export Template and the task names and resource names are listed
 