In MS Project, can I easily paste a group of tasks multiple times

D

Deb

I have a development project w/ 100+ high level tasks. Each one is made up
of a sub-set of 10 detailed tasks that are the same.

Is there an easy way to copy these 10 detailed steps and paste them quickly
into my 100+ higher level tasks?
 
J

Jan De Messemaeker

Hi,

Yes.
Select them by the ID, Edit Copy, paste anywhere.
Pay attention to the indenting (outline level).
HTH
 
D

Deb

Thanks for your help. Thought that was the only way...a bit labor intensive
on this large project, but oh well!

Thanks again!
 